Executive summary
Private 5G is procurable for grid OT. The system around it is what you are buying.
A distribution network operator (DNO) that wants to carry protection signalling, control and SCADA traffic over a private 5G network can do so today with commercially available core and radio equipment. The radio is rarely the problem. The problem is that nobody sells the system: the spectrum decision, the core, the radio, the device at the operational technology (OT) boundary, the security evidence and the lifecycle plan arrive from different suppliers, and the integration risk lands on the buyer.
This guide is written for the people who carry that risk: OT and telecoms engineers, cyber and assurance leads, and procurement teams inside a DNO or another critical national infrastructure (CNI) operator. It explains what a stand-alone non-public network (SNPN) is, which timing requirements actually drive the architecture, how UK spectrum works for a utility in 2026, what to demand at the OT boundary, and how to read the evidence a vendor puts in front of you.
Novomorphic builds one part of that system: the edge device between substation equipment and the 5G network. We are not a radio or core supplier, and this guide says so wherever it matters. It quotes no performance figure for our own hardware, which is still in development.
Scope
What this guide covers, and what it leaves to others
What an SNPN is in 3GPP terms, and why a slice of a public network is not the same thing for OT traffic.
The timing classes in IEC 61850 and 3GPP TS 22.104 that decide whether a design is adequate, with the numbers and where they come from.
UK spectrum for utilities: what Ofcom licenses today at 3.8 to 4.2 GHz, and where the 450 MHz question stands.
The OT boundary device: what an industrial PC and modem give you, what a purpose-built edge platform is meant to add, and how to tell the difference with evidence rather than slides.
Security and assurance: how the NCSC Cyber Assessment Framework maps to questions you can put to every vendor.
A procurement checklist in six steps, and the questions we would expect a well-run DNO to ask us.
It does not cover radio planning in detail, core vendor selection, or the commercial structure of a managed service. Those are real decisions. They belong with your systems integrator.
Definitions
An SNPN is a network you operate. A slice is a network someone else operates for you.
3GPP introduced non-public networks (NPNs) in Release 16 and refined them in Release 17. The specifications define two deployment models. A stand-alone non-public network (SNPN) is operated by the NPN operator and does not rely on network functions provided by a public land mobile network. A public-network-integrated NPN (PNI-NPN) is deployed with the support of a public operator, typically as a slice or a dedicated access point on the public core.
The distinction matters for OT because of who holds the keys and who answers for availability. In an SNPN the core, the subscriber database, the user-plane function and the policy decisions sit inside your security boundary and your change control. During a wide-area power outage, a public mobile network may lose backhaul or site power at exactly the moment a DNO needs to coordinate fault isolation and restoration. An SNPN with its own resilient power and transport does not share that failure mode, which is the resilience argument Innovate UK made when it framed the SNPN 5G Assured Integration competition around secure, resilient, real-time connectivity for OT environments under the full control of the adopting organisation.
A PNI-NPN is not wrong. It is the right answer for traffic that is not safety-related and that benefits from national coverage: field workforce applications, non-critical telemetry, backup paths. The procurement mistake is to specify one model for all traffic classes. Most DNOs will end up with both, and the architecture should say which traffic goes where and why.
Requirements
Four timing classes decide the architecture. Write them down before anyone draws a diagram.
Protection trip, transmission class
IEC 61850-5 Type 1A trip messages under performance class P2 or P3 must arrive within 3 ms. Transmission substations are typically specified to P2 and P3. This is the class that a wireless hop will struggle to meet on its own.
IEC 61850-5, vendor summary cited
Protection trip, distribution class
Under performance class P1, the class distribution substations are typically specified to, Type 1A trip messages have 10 ms. Other fast signals (Type 1B) have 100 ms under P1 and 20 ms under P2 and P3.
IEC 61850-5
Differential protection over a network
3GPP TS 22.104 lists high-speed current differential protection with an end-to-end latency of 5, 10 or 15 ms, a transfer interval of 1 or 2 ms, message sizes under 245 bytes and 99.999% communication service availability.
3GPP TS 22.104 Release 19
Frequency and voltage control
The same specification gives primary frequency control about 50 ms end to end and distributed voltage control about 100 ms, each at 99.999% availability, over service areas up to 100,000 square kilometres and up to 100,000 devices.
3GPP TS 22.104 Release 19
The 3GPP figures are service requirements written by the standards body, not measurements of any network. Your own network will meet them or not depending on configuration, load and the device at each end.
Where the budget goes
Latency is spent in five places. Only two of them belong to the radio.
A GOOSE message from an intelligent electronic device (IED) to a remote peer or to SCADA passes through the OT boundary device (the user equipment, or UE), the air interface, the user-plane function in the core, the transport to wherever the application sits, and the application's own ingest. Every one of those takes time, and only the air interface and the user-plane function are what a radio vendor sells you.
As an illustrative planning allocation, take roughly 0.5 ms in the UE, 2 ms over the air, 1 ms through the user-plane function and 0.5 ms in backhaul for the user-plane path, about 4 ms in total before the application has done anything. Those are round planning figures for a worked example, not measurements of any network. The shape is what matters: the UE and the application ingest are where a buyer has the most control and where the least attention is usually paid.
Two conclusions follow. First, a 3 ms transmission-class trip over a single wireless hop is not a reasonable procurement requirement for 2026 equipment, and a vendor who tells you otherwise should be asked for the distribution, not the mean. Second, 10 ms distribution-class protection, 15 ms differential protection, and 50 to 100 ms control are achievable budgets, provided the device at the boundary processes the protocol deterministically and the core is on site. The design decision is therefore about the UE and the user-plane placement before it is about radio.
Jitter matters as much as latency. Protection schemes are designed around worst case, not typical. A boundary device that handles IEC 61850 in software on a general-purpose operating system will show a long tail under load, because that is what interrupt-driven software does. The fair question for any boundary device is the 99.99th percentile over a stated sample count under a stated load, with the configuration disclosed.
Spectrum
What a UK utility can license in 2026
| Criterion | Who licenses it | Coverage per site | Status | Fits |
|---|---|---|---|---|
| 3.8 to 4.2 GHz, shared accessInside the n77 range that commercial 5G radios support. Low power: any number of base stations within a 50 metre radius. Medium power: one base station and its terminals. | Ofcom, per site | Campus or site | Available now | Substations, depots, high bandwidth |
| 1800 MHz and 2300 MHz, shared accessSmall paired and unpaired blocks. Better propagation than 3.8 GHz, far less bandwidth. | Ofcom, per site | Site | Available now, small blocks | Site coverage where 3.8 GHz is congested |
| 450 MHz regionUp to 2 x 5 MHz within 450 to 470 MHz was one of Ofcom's 2023 candidate bands. Heavily used, reversed band plan, longer timescale. | Ofcom, no utility award | Wide area | Candidate band, no award timetable | Wide-area monitoring and control, if awarded |
| Public network sliceA public-network-integrated NPN in 3GPP terms. The operator holds the core and the credentials. | Mobile operator | National | Commercial | Non-critical traffic, field apps, backup |
3.8 to 4.2 GHz, shared access
Inside the n77 range that commercial 5G radios support. Low power: any number of base stations within a 50 metre radius. Medium power: one base station and its terminals.
- Who licenses it
- Ofcom, per site
- Coverage per site
- Campus or site
- Status
- Available now
- Fits
- Substations, depots, high bandwidth
1800 MHz and 2300 MHz, shared access
Small paired and unpaired blocks. Better propagation than 3.8 GHz, far less bandwidth.
- Who licenses it
- Ofcom, per site
- Coverage per site
- Site
- Status
- Available now, small blocks
- Fits
- Site coverage where 3.8 GHz is congested
450 MHz region
Up to 2 x 5 MHz within 450 to 470 MHz was one of Ofcom's 2023 candidate bands. Heavily used, reversed band plan, longer timescale.
- Who licenses it
- Ofcom, no utility award
- Coverage per site
- Wide area
- Status
- Candidate band, no award timetable
- Fits
- Wide-area monitoring and control, if awarded
Public network slice
A public-network-integrated NPN in 3GPP terms. The operator holds the core and the credentials.
- Who licenses it
- Mobile operator
- Coverage per site
- National
- Status
- Commercial
- Fits
- Non-critical traffic, field apps, backup
Band descriptions summarised from Ofcom's shared access licence page and its utilities spectrum call for input and updates. Check the current Ofcom guidance before specifying; the fees and conditions change.
Spectrum in practice
Site coverage is licensable today. Wide-area coverage is still a policy question.
Ofcom's shared access licence framework, first published in December 2019 and still being updated, lets any organisation apply for local spectrum in four bands: 1781.7 to 1785 MHz paired with 1876.7 to 1880 MHz, 2320 to 2340 MHz and 2390 to 2400 MHz, 3800 to 4200 MHz, and 24.25 to 27.5 GHz. A low power licence permits as many base stations as needed within a 50 metre radius; a medium power licence authorises a single base station with its fixed, nomadic or mobile terminals. Annual fees in rural areas run from £80 for a small 1800 MHz channel to £800 for 100 MHz in the 1800, 2300 or 3800 to 4200 MHz bands, with urban medium power fees in the 1800 and 3800 to 4200 MHz bands at double those rates.
For a substation, a depot or a primary site, this is a workable answer now. 3.8 to 4.2 GHz offers the bandwidth for machine vision, drones and the video a field operations service wants, and the band sits inside the n77 range that commercial 5G radios already support. Its limitation is physics: coverage per site is small, so it is a site technology, not a network-wide one.
Wide-area coverage for thousands of secondary substations and remote assets wants sub-1 GHz spectrum, which is why utilities across Europe have gravitated to the 450 MHz region. In the UK, Ofcom opened a call for input in June 2023 on potential spectrum bands to support utilities sector transformation, listing candidate bands including up to 2 x 5 MHz within 450 to 470 MHz for Great Britain and Northern Ireland, 400 MHz and 800/900 MHz options for Northern Ireland only, the 700 MHz public safety pairing, and 1900 to 1920 MHz. Ofcom described the 450 MHz band as heavily used across the UK, with a reversed band plan relative to European harmonisation, and said it would likely take longer to make available than other bands.
Ofcom received 36 responses and reported in November 2023 that stakeholders favoured sub-1 GHz bands. In March 2025 it reported modelling showing LTE use of the 400 MHz band is viable in Northern Ireland without affecting the Fylingdales radar, subject to arrangements with the Ministry of Defence and the existing licensee. As of this writing Ofcom has announced no award process or timetable for a utility band in Great Britain. A DNO specifying a network in 2026 should therefore plan for site coverage on shared access spectrum, keep the architecture radio-agnostic enough to add a sub-1 GHz layer later, and make sure its systems integrator can demonstrate that the same core and the same boundary devices work across both. That multi-band, multi-vendor requirement is precisely what the GRID-5G consortium set out to demonstrate at PNDC with 3.8 GHz and 450 MHz air interfaces from different suppliers, and the demonstration is where the evidence for it will come from.
Procurement
Six steps, in this order
Classify the traffic before choosing anything
List every application that will use the network and assign each a timing class, an availability requirement and a consequence of failure. Use the IEC 61850 performance classes and the 3GPP TS 22.104 rows as the vocabulary, so that every vendor is answering the same question. Decide which classes must be SNPN-only and which may use a public network.
Decide spectrum per layer
Site coverage on shared access spectrum at 3.8 to 4.2 GHz is available now. Treat wide-area sub-1 GHz as a future layer and require that the architecture, the core and the boundary devices can absorb it without redesign. Ask your spectrum adviser, not your radio vendor, to own this decision.
Appoint an accountable integrator
Innovate UK made a systems integrator with clear accountability for overall system design, multi-vendor interoperability, and security and resilience assurance a condition of its SNPN competition. Make it a condition of yours. The integrator owns the interfaces; component vendors own components.
Specify the OT boundary device as a system component
The device between IEDs and the radio decides the latency tail, the protocol conformance and the local security posture. Require IEC 61850 conformance evidence, a stated latency distribution under load, a hardware root of trust, signed updates and a substation environmental rating. Treat an industrial PC and modem as the baseline to beat, not as the default.
Buy the assurance with the network
Ask for independent security and interoperability evidence against the NCSC Cyber Assessment Framework objectives, produced by someone who did not build the system. Specify what must be delivered as documents you can hand to your own assurance process, not as a vendor certificate.
Plan the twenty-year life
Substation equipment is in service far longer than a mobile network generation. Require a field update path, a parts availability plan, cryptographic agility including a route to the NIST post-quantum standards, and a stated position on who maintains the core software in year twelve.
The OT boundary
An industrial PC and a modem will usually work. Decide what usually costs.
The conventional way to put a substation on a mobile network is an industrial PC running the protocol stack, a serial or Ethernet connection to the RTU or IEDs, and a 5G modem. It is cheap, well understood and widely deployed, and in GRID-5G it is the deliberate low-risk baseline: PNDC has already demonstrated SCADA over 5G this way under the earlier Constellation programme.
What such a device cannot do is make timing a design property. IEC 61850 GOOSE and Sampled Values are handled in software on a general-purpose operating system, so the latency distribution depends on everything else the processor is doing. Security depends on a software stack that was not designed for a twenty-year unattended life. Power and thermal behaviour are whatever the industrial PC vendor shipped.
The alternative Novomorphic is developing in GRID-5G is an FPGA-based edge platform that processes IEC 61850 GOOSE, Sampled Values and precision time in hardware, runs anomaly detection locally on the operational data, and is packaged for the substation environment with GaN power conditioning. The programme sets out to show that timing at the boundary can be a property of the design rather than of the load, through hardware-in-the-loop trials against live 11 kV to low-voltage assets at PNDC. The comparison that matters is this platform against the PC and modem baseline on latency, jitter, power, footprint and recovery behaviour.
Whoever supplies your boundary device, treat the claim the same way: ask for the measurement conditions, the sample count, the percentile, the baseline and the test environment. A vendor who cannot tell you which of their figures are plans and which are measurements will not be able to tell you in a dispute either.
Security and assurance
Map every vendor question to a CAF objective
A. Managing security risk
Governance, risk management, asset management and supply chain. Ask who owns the risk register for the network, how every component and firmware image is inventoried, and what the vendor can show about the provenance of its own software and hardware.
Principles A1 to A4
B. Protecting against attack
Identity and access, data security, system security, resilient networks and systems. Ask how subscriber credentials are provisioned and revoked, how the boundary device boots and updates, and how the network degrades under the loss of a core site.
Principles B1 to B6
C. Detecting events
Security monitoring and threat hunting. Ask where OT traffic is monitored, whether anomaly detection runs locally when backhaul is lost, and what the detection evidence looks like. CAF v4.0 strengthened this objective.
Principles C1 and C2
D. Minimising impact
Response and recovery planning, lessons learned. Ask what the restoration sequence is for the network itself during a black start, and who rehearses it.
Principles D1 and D2
The NCSC published CAF v4.0 on 6 August 2025, adding a section on understanding attacker methods, a supply chain section on software developed and maintained securely, stronger detection expectations and coverage of AI-related risk. Nearly all UK cyber regulators use the CAF, and it applies to operators of essential services under the NIS Regulations across energy, health, transport, digital infrastructure and government.
Limits
What this guide cannot settle for you
- This guide gives you the vocabulary, the public requirements and the questions
- It is written by a company that builds one component in the chain and has an interest in the answer
- We have tried to say plainly where that interest shows
Not included
It does not replace a radio plan for your sites, a core vendor evaluation, a commercial model for managed services, or your own CAF self-assessment. It does not tell you whether private 5G is justified for your network; that depends on your fibre estate, your asset count and your regulatory settlement, which Ofgem fixed for RIIO-ED2 at £22.2 billion of allowed expenditure across the distribution companies for April 2023 to March 2028.
Due diligence
Ten questions to put to every vendor, including us
Which 3GPP release and which NPN model does the network implement, and where does the subscriber database sit?
For each traffic class we specified, what is the measured end-to-end latency at the 99.99th percentile, over how many samples, under what load, and who witnessed it?
Which bands and which radios have you integrated with this core, and can you show the same boundary device working across more than one air interface?
What does the network do during a site power loss lasting eight hours, and what has been tested rather than designed?
Which IEC 61850 conformance evidence exists for the boundary device, against which edition, and who ran the test?
How does the boundary device boot, how are updates signed, and what is the hardware root of trust?
Who produced the security and interoperability assurance, and did they build any part of the system?
What is the parts availability and software maintenance commitment at year ten and year fifteen?
Which of the figures in your material are measured, and which are design figures or objectives?
What is not in scope of your offer, and who do you expect to own it?
Where the evidence will come from
GRID-5G is built to answer these questions in public
GRID-5G is an 18-month Innovate UK collaborative research and development project under the SNPN 5G Assured Integration competition, which opened on 3 March 2026 with up to £18.5 million available, projects of £2 million to £4 million, and a start date of 1 August 2026. The consortium, led by PNDC at the University of Strathclyde, is integrating a multi-vendor 5G core and radio architecture with Novomorphic's edge platform and an orchestration layer, and trialling it against live 11 kV to low-voltage assets with real IEDs, RTUs and SCADA gateways. Independent security and interoperability assurance is part of the scope, and the public outputs are intended to be technical reference architectures, interoperability evidence and security assurance documentation that a DNO can use directly in procurement.
For Novomorphic, the programme is designed to produce the comparison between a purpose-built boundary device and a PC and modem that this guide keeps asking for. If you are specifying a network before then, we are glad to talk through the architecture, and we will say so if we think you do not need custom hardware at your OT boundary.