Novomorphic
GRID-5GIn progressFunded by Innovate UK

From FPGA prototype to live-grid validation

Taking our secure edge AI hardware to trials on a live grid over private 5G.

Our role
Work package lead for Secure Edge AI Hardware and OT Interface (WP3)
Funder
Innovate UK
Started
August 2026
Duration
18 months
Now
Architecture and interfaces
Next
Bench

Why it matters

Predictably, not usually

Modern energy networks depend on communications that have to work predictably, not usually. As distributed generation grows and the network digitises, the volume of operational data and the timing sensitivity of protection messaging both rise. The answer has to work locally, rather than as a round trip to a datacentre over a public network.

During a blackout or black-start event the public mobile network may itself be unavailable. A private network that keeps operating is what lets an operator coordinate fault isolation and restoration. GRID-5G exists to produce the evidence a distribution network operator actually needs before adopting anything at the OT boundary.

PROGRAMME · GRID-5G · ARCHITECTURE

Substation to control room, hop by hop

Tap a hop to see where our edge platform sits.

NovomorphicEdge platform

GOOSE, SV and PTP handled in hardware.

Inside the platform

We are not the RAN or core supplier.

Three use cases

What the consortium will demonstrate

  • SCADA over 5G from an FPGA end point

    Novomorphic’s platform speaking IEC 61850 directly over the private network. The highest innovation and the highest risk in the programme; it starts from an FPGA prototype.

    Novomorphic, WP3

  • SCADA over 5G, conventional path

    An industrial PC and modem, as already used at the testbed on an earlier programme. The low-risk baseline the edge platform is compared against.

    Consortium, WP6

  • Services over the network

    Inspection and field-operations applications across substation and field assets, showing the network carrying services beyond protection and control.

    Systems integrator

How it will be proven

On a live network, against what you would otherwise deploy

Validation is planned on PNDC’s 11kV-to-LV distribution network, with live IEDs, RTUs, SCADA gateways and IEC 61850 digital substation equipment. Hardware-in-the-loop scenarios cover fault handling, FLISR sequences and blackout and black-start conditions.

The comparison that matters to a network operator is against what they would otherwise deploy: an industrial PC and a modem. The two paths are compared under the same scenarios on latency, jitter, power, footprint and recovery behaviour.

The radio layer is deliberately mixed: 3.8 GHz for site-wide bandwidth and 450 MHz for wide-area coverage, across more than one radio and core vendor. That makes the outcome relevant to a procurement decision rather than to one installation.

PROGRAMME · GRID-5G · VALIDATION

Five phases, from bench to live grid

Pick a phase to see which comparisons it builds.

Phase BBenchMonths 3 to 10
ANowBCDE
Latency
Jitter
Power
Footprint
Recovery
Bench
Testbed

Each measure set side by side with an industrial PC and modem.

Phases as published on the GRID-5G programme page.

Scope boundary

Our part, and what is not ours

Novomorphic is not the RAN or core supplier. GRID-5G trials the edge platform within a wider private 5G architecture delivered by the consortium.

Technical detail

What our work package (WP3) delivers

  • FPGA firmware v1.0: the OT protocol engine for GOOSE, SV and PTP, prototype build.

  • Inference engine with OT anomaly-detection models trained on testbed traffic data.

  • A complete Secure Edge AI hardware platform, trialled on the testbed: FPGA firmware, RF electronics, power electronics, enclosure.

  • A hardware integration report and substation deployment specification.

Project outputs are intended to include reference architectures, interoperability evidence and security assurance, while Novomorphic implementation IP remains protected.

PROGRAMME TIMELINE

Where the programme is

Where the programme is now, and what comes next.

Phase AIn progress

Architecture and interfaces

Requirements, system-level architecture and standards alignment with the consortium (WP1). Ends with DNO requirements captured and the initial end-to-end architecture agreed, which gates integration work.

WhenMonths 1 to 3

Where the programme is, every milestone

  1. Phase A, Months 1 to 3: Architecture and interfaces (In progress). Requirements, system-level architecture and standards alignment with the consortium (WP1). Ends with DNO requirements captured and the initial end-to-end architecture agreed, which gates integration work.
  2. Phase B, Months 3 to 10: Bench (Planned). Protocol engine design and the first prototype firmware build. Interface alignment checkpoint with the systems integrator at month 6. Prototype hardware ready for bench integration and the first bench tests.
  3. Phase C, Months 4 to 10: AI, power and EMC (Planned). Inference engine integration, GaN power conditioning and packaging. EMC pre-compliance scans at months 6 and 9. Orchestration API ready at month 9 for closed-loop integration.
  4. Phase D, Months 10 to 16: Testbed (Planned). Hardware deployed at PNDC and hardware-in-the-loop validation against real IEDs, RTUs and SCADA on live grid assets (WP6). Security and resilience assurance runs alongside (WP5).
  5. Phase E, Months 16 to 18: Validated (Planned). The platform and its documentation complete, with the hardware integration report and the substation deployment specification, alongside the consortium’s reference architecture.

7 pages, PDF

GRID-5G programme summary

The public summary of GRID-5G: the problem, where the Novomorphic edge platform sits in the architecture, the work package deliverables, the trial plan at PNDC and the phases.

What’s inside

  • The problem GRID-5G addresses, and where our edge platform sits
  • Our work package and what it delivers
  • Who delivers it, and the phases

Read next: The buyer's guide to private 5G for grid OT

ARCHITECTURE

Where the platform sits

IED → Novomorphic edge platform → gNB → 5G core and UPF → SCADA, with multi-vendor paths through the network layer: 3.8 GHz (n78) and 450 MHz (n31) radios, more than one core. Novomorphic’s scope is the edge platform and the OT interface.

01 · Intelligence

Deterministic OT processing

An FPGA-based protocol engine handling IEC 61850 GOOSE, SV and PTP in hardware, with DNP3 and IEC 60870 bridging, so timing is a design property rather than a measured average.

Novomorphic’s part

Novomorphic owns work package deliverable D3.1, the protocol engine firmware.

Where the platform sits, full text

Deterministic OT processing (Intelligence)
An FPGA-based protocol engine handling IEC 61850 GOOSE, SV and PTP in hardware, with DNP3 and IEC 60870 bridging, so timing is a design property rather than a measured average. Novomorphic’s part: Novomorphic owns work package deliverable D3.1, the protocol engine firmware.
On-device intelligence (Intelligence)
OT anomaly-detection models trained and validated on testbed traffic data, running locally on the operational data without sending it off site. Inference outputs feed the orchestration layer for closed-loop RF optimisation. Novomorphic’s part: Novomorphic owns work package deliverable D3.2, the inference engine and models.
RF interface electronics (Signal)
The interface between the edge platform and the private 5G network, inside a multi-vendor architecture delivered by the consortium. Novomorphic’s part: Novomorphic owns the RF interface electronics.
GaN power conditioning (Control)
Power conditioning for a platform that never turns off, inside a real power and thermal budget. Novomorphic’s part: Novomorphic owns the power stage design.
Substation-hardened packaging (Control)
Designed for the substation environment, covering temperature, EMC, isolation and service life. EMC pre-compliance scans are planned at months 6 and 9, with formal conformance work in the testbed phase. Novomorphic’s part: Novomorphic owns packaging and EMC.

Talk to the GRID-5G team

A briefing covers architecture fit, current maturity, the route to silicon or deployment, and the security and IP boundaries. It is a technical conversation.

An engineer reviews every enquiry.

We can sign an NDA before any technical detail is exchanged.

What happens next

1

An engineer reads it

Not a form-handler. Whoever owns the relevant discipline.

2

We come back with a technical view

Including if we think you do not need us.

3

If it looks like a fit, a short technical call

Then, if it is useful, a scoped workshop, feasibility study or evaluation.